Break down #32 into implementable work units — Phase 6: Remaining components + CI coverage gate: tests for navigation-menu, menubar, pagination, breadcrumb, command, carousel, calendar, chart, form, sidebar, resizable, scroll-area, input-otp, field, … #41

Closed
opened 2026-05-21 18:34:15 +00:00 by Mark · 2 comments
Owner

Files: app/.forgejo/workflows/ci.yml, app/src/components/ui/command.test.tsx, app/src/components/ui/navigation-menu.test.tsx, app/src/components/ui/carousel.test.tsx, app/src/components/ui/breadcrumb.test.tsx
Depends on: P3, P4, P5


Post-completion: When each phase is complete, comment on #32 with a summary of what was implemented.


Decomposed from redlens#34

## Phase 6: Remaining components + CI coverage gate: tests for navigation-menu, menubar, pagination, breadcrumb, command, carousel, calendar, chart, form, sidebar, resizable, scroll-area, input-otp, field, table, alert, alert-dialog, empty, item, kbd, spinner, sonner, aspect-ratio, input-group, button-group, collapsible, resizable; then add coverage reporting to CI **Files:** app/.forgejo/workflows/ci.yml, app/src/components/ui/command.test.tsx, app/src/components/ui/navigation-menu.test.tsx, app/src/components/ui/carousel.test.tsx, app/src/components/ui/breadcrumb.test.tsx **Depends on:** P3, P4, P5 --- **Post-completion:** When each phase is complete, comment on #32 with a summary of what was implemented. --- _Decomposed from [redlens#34](https://forgejo.tail018ac4.ts.net/Mark/redlens/issues/34)_
Author
Owner

GSD VERIFY phase found no changes after implementation.
Worker output:

GSD VERIFY phase found no changes after implementation. Worker output:
Author
Owner

This issue has been decomposed into the following sub-issues:

# Title Phase Scope
#42 Break down #32 into implementable work units — Phase 6: Rema Files: app/.forgejo/workflows/ci.yml, app/src/components/ui/command.test.tsx

Each sub-issue has been labeled with needs-triage and will be evaluated by the triage pipeline before queue routing.

This issue has been decomposed into the following sub-issues: | # | Title | Phase Scope | |---|-------|-------------| | #42 | Break down #32 into implementable work units — Phase 6: Rema | **Files:** app/.forgejo/workflows/ci.yml, app/src/components/ui/command.test.tsx | Each sub-issue has been labeled with `needs-triage` and will be evaluated by the triage pipeline before queue routing.
Mark closed this issue 2026-05-23 16:59:11 +00:00
Sign in to join this conversation.
No description provided.